J&M Murdoch

DC fast charging from a 32A supply.

£300kgrid upgrade deferred, live in a day
CustomerJ&M Murdoch & Son
SectorFleet depot
LocationGlasgow, Scotland
SystemMAX300 · On-grid

The challenge

What they faced

J&M Murdoch wanted to electrify its depot fleet, but its site supply could not run DC fast chargers. The alternative was a grid upgrade costing around £300k and a long wait for the connection.

What we deployed

How MAX solved it

A stationary MAX300 charges from a 32A supply and buffers satellite DC fast chargers from Chargepoly, delivering high power whenever vehicles plug in. It was installed and running in a day.

£300kgrid upgrade deferred
1 dayto deploy
32Asupply is all the depot needed
Andrew Murdoch
"Allye's battery install was quick and seamless, enabling us to install DC fast EV chargers on site without waiting years for a grid connection."
Andrew Murdoch, J&M Murdoch

Want results like these?

Tell us about your site and we'll model the savings before you commit.